Cefn Glas Residential Home Roofing Replacement

Project Overview

TW Group (South Wales) LTD was appointed by POBL to carry out essential roofing works at Cefn Glas Residential Home. Initially planned as a repair project due to persistent roof leaks, the scope expanded into a full re-roofing programme following the condemnation of the existing structure.

To ensure minimal disruption to the vulnerable and elderly residents, the works were strategically phased, allowing for a structured and safe execution while maintaining operational efficiency within the care home.


Project Phases & Key Works

Phase 1 – Pitched Roofing

  • 600m² of Marley Edgemere tiles replaced to enhance durability and weather resistance.
  • Completed on time and within budget
  • Improved weather-tightness and aesthetic appearance.

Phase 2 – Flat Roofing

  • 180m² of single-ply roofing installed to modern standards.
  • Successfully delivered within the allocated budget of £70,000.
  • Increased energy efficiency and extended roof longevity.

Phase 3 – Pitched Roofing

  • 600m² of Marley Edgemere tiles replaced to enhance durability and weather resistance.
  • Completed on time and within budget
  • Improved weather-tightness and aesthetic appearance.

Health, Safety & Project Management Considerations

Traffic Management Plan

  • A coordinated plan was implemented to ensure minimal disruption to residents and staff.
  • Strict scheduling of material deliveries to avoid peak operational hours.
  • Worked in collaboration with all contractors to optimise logistics and enhance site efficiency.

Site Safety Measures

  • Regular safety inspections and compliance checks conducted throughout the project.
  • Daily safety briefings for all site personnel to reinforce best practices.
  • Risk assessments and method statements (RAMS) ensured that all works complied with the highest health and safety standards.

Noise Pollution Management

  • Implemented specialised noise control measures to safeguard vulnerable residents.
  • Noisy tasks scheduled during agreed-upon hours to minimise disruption.
  • Noise barriers and mufflers used to mitigate sound impact within and around the care home.

Overall Impact & Project Success

The phased delivery approach allowed for:

  • Efficient budgeting and staged investment for the client.
  • Minimal disruption to residents, maintaining a safe and comfortable living environment.
  • Enhanced durability, weather protection, and energy efficiency of the residential home.
  • A collaborative, well-planned, and client-focused execution.

This project showcases TW Group’s expertise in delivering critical infrastructure upgrades within occupied healthcare environments, ensuring a balance between functionality, safety, and quality.